|

|
Numbers
to call if you see or hear of something that concerns you in the Hyde
Creek Watershed |
Extensive
continued urbanization of the central portion of the watershed has
negatively affected Hyde Creek and its tributaries. These effects
include increased channel instability and bank erosion, non-point
source pollution and reduced low summer flows. The objective of the
2001 stream rehabilitation project - with assistance from the Hyde
Creek Hatchery Group, Provincial Ministries, Fisheries and
Oceans,Canada, and the City of Port Coquitlam - was to offset the
effects of urbanization by reducing stream degradation as well as
enhancing fish habitat.
Hyde Creek
Before 2000 Restoration Project
|
 |
This project
was a continuation of recommended stream enhancements outlined in the
Hyde Creek Fish Habitat Enhancement Plan conducted by Coast River
Environmental Services Ltd. This phase of restoration was carried out
from Coast Meridian Road to Hyde Creek Recreation Center and was
conducted during the fisheries working window (mid August to
beginning of September) in order to minimize the impact on resident
salmon populations. |
This phase of
restoration covered approximately 800 meters in Hyde Creek. A total
of eight pools were constructed along the channel length at about 30-meter
intervals. In an attempt to recreate the structural complexity of
natural stream channels, rock weirs were placed at the upstream end
of each pool to promote localized scouring during high flows. Large
wood was anchored in each pool to provide cover for juvenile
salmonids particularly during low flow periods.
DFO
Recreates New Creek Bed
|
 |
Gravel was
excavated from the creek bed to a depth of 1.0 meter below the
existing streambed. Some trees were removed; however, large trees
were used as root wads in the pools and were incorporated into the
weir construction to help stabilize the banks at
each side of the weir. Vegetation was replanted as necessary by the
Watershed Society.
The
construction of the Newbury Weirs and pools in Hyde Creek was
completed on budget and within the fisheries working window timeframe
(second week of August to first week in September) through the
assistance and cooperation of the associated parties. |
New Creek
Bed Completed
|
 |
An intake and
connection point into the stream was also created and the majority of
excavated material was used for on-site berm construction. Prior to
instream enhancement and off-channel pond creation, little spawning
habitat existed. Stream character included little variation and
lacked pool-riffle sequences, undercut banks or large instream logs.
The Hyde Creek Watershed Society successfully implemented instream
habitat enhancement as well as pond creation that has been shown to
be successful in producing large numbers of Coho smolts.
|
Top
of page |